How to Schedule Excavation, Grading, Concrete, and Utilities Around Frost Dates and Spring Thaw

In Teton Valley, the calendar matters just as much as the blueprints. Between deep frost, wet springs, and short warm-weather windows, even the best-planned build can hit costly delays if you don’t schedule work in the right order.

Shawn at ParkFab has spent years timing projects to dodge frostbite on your foundation and mud up to your knees — here’s how he approaches seasonal planning so your build actually stays on track.


1. Start with Frost Dates, Not Just Permits

We’re not building in Phoenix. Frost depth in the valley can hit 48 inches or more. That means:

  • Excavation & foundation work need to be done before the ground freezes solid, or you’re paying for frost ripping and heaters.

  • Helical piers or frost-protected foundations can extend your season — but they still need proper planning.

Shawn always checks local weather patterns before setting start dates.


2. Grade Before the Ground Gets Soup-Wet

Spring thaw here isn’t gentle — it’s a weeks-long slop fest. Trying to grade in April? You’ll sink equipment, rut your site, and compact wet soil so badly that drainage will never be the same.

The sweet spot for grading is late summer into early fall, when the ground is dry but not frozen. This is also the perfect time to:

  • Install driveway base

  • Set up temporary drainage

  • Shape berms for windbreaks or snow control


3. Pour Concrete in the Goldilocks Zone

Concrete hates extremes. Too cold, and it won’t cure right. Too hot and dry, and it can crack before it sets.

In Teton Valley, your best concrete windows are:

  • Late spring to early fall — but only after the ground is dry and stable

  • Always with curing blankets or additives if temps are borderline

Shawn won’t pour a foundation when there’s frost in the footings — period.


4. Utilities: Don’t Leave Trenches to Freeze

Water, sewer, electrical, propane — all need trenching, and frozen ground can turn a one-day job into a week-long fight.

  • Bury lines below frost depth to avoid winter failures

  • Schedule utility installs before consistent overnight freezes

  • Backfill immediately to protect pipes and wiring


5. Build a Buffer Into Every Season

The valley is unpredictable. One early storm or a week of rain can push you back. Shawn always pads timelines to account for:

  • Mud delays in spring

  • Smoke delays in summer

  • Early snow in fall

Rushing work in bad conditions almost always costs more than waiting for the right window.


Work With Someone Who Knows the Local Calendar

Seasonal planning in Teton Valley isn’t just about convenience — it’s about protecting your investment. Shawn’s crew knows when to push, when to pause, and how to keep progress moving without creating problems for the next phase.